Okanagan Capacity Mitigation Project
We’re planning to increase our capacity in the Okanagan by adding approximately 30 kilometres of new gas line. This project will be an extension of our existing natural gas system, connecting along Penticton’s eastern border and extending north, just beyond Chute Lake.
About this project
The Okanagan Capacity Upgrade project is driven by the increasing demand we are facing in the region, and will allow us to meet energy needs now, and well into the future.
This expansion would strengthen our system for approximately 105,000 homes and businesses in the Okanagan that rely on our natural gas service every day.
Flyover of proposed route
- 30 kilometres of new gas line driven by increased demand
- extension of existing system will keep pace with regional growth now and into the future
- will also strengthen our system for approximately 105,000 current customers
- connecting to our existing system at Ellis Creek (Penticton) and Chute Lake
- majority of route alongside existing FortisBC rights of way to minimize environmental footprint
Project timelines and next steps
We filed our application with the British Columbia Utilities Commission (BCUC) on November 16, 2020. In April and May 2020, we held telephone town halls where the community could learn more about the project, get their questions answered and provide feedback. We will continue to provide engagement opportunities throughout the project.
We anticipate a decision in 2023. If approved, we expect project construction will take place between 2023 and 2024.
At this time, we estimate this project will cost approximately $271 million, which works out to an annual increase of approximately $9.00 per year for the typical, residential customer in 2024.
Engagement began
BCUC application filed
We filed our project application for a Certificate of Public Convenience and Necessity with the BC Utilities Commission (BCUC). View our application.
Read more
Read less
Anticipated BCUC decision
Anticipated construction
In service
November 16, 2020
Major step forward for the Okanagan Capacity Upgrade project
September 30, 2020
Wildfire delays some early engineering work
July 31, 2020
Early works along the route
May 6, 2020
May 20th, 2020
April 15, 2020
FortisBC proposes new gas line project to meet Okanagan growth
April 15, 2020
Telephone town halls
Testing form submission - gmail
Answered on:
Jan 31, 2025
UAT by Diego G.
Answered on:
Mar 9, 2023
Why is FortisBC still investing in natural gas instead of exploring cleaner energy solutions?
Answered on:
Jul 22, 2022
Who will benefit from the project?
Answered on:
Jun 11, 2021
Will this project service new properties not currently connected to FortisBC’s natural gas system?
Answered on:
Jun 11, 2021
Why does the route run alongside existing rights of way in some places, but not others?
Answered on:
Jun 11, 2021
Can I see a detailed map of the proposed route?
Answered on:
Jun 11, 2021
How do I get more information on the project?
Answered on:
Feb 25, 2021
Where would the new gas line be built?
Answered on:
Dec 9, 2020
Why build the Okanagan Capacity Upgrade project?
Answered on:
Dec 3, 2020
Pagination
Summer 2025
Time
3:00 p.m. to 4:00 p.m. PST
Format
Partnering with communities
We’re committed to the South Okanagan and are pleased to be active in these communities where we live and work. In addition to regularly engaging residents and Indigenous communities on our services and energy infrastructure, we’re committed to investing in and supporting the region in a variety of ways.
This includes contributing to, and participating in, local community events such as the Pow Wow Between the Lakes event in Penticton—a celebration of the culture and traditions of the Syilx (Okanagan) people. We’ve also supported community projects such as the Three Blind Mice Trails Improvement Project—an initiative headed by the Penticton and Area Cycling Association to develop mountain bike trails in the region.
As project planning continued, we built on this relationship by signing a three-year funding partnership with PACA to maintain and improve safety on local bike trails. Read more about this partnership and the trained regional area trail stewards who began upgrades to the Bronco Trail in summer 2020. We’ll continuing exploring other opportunities to partner with the local community as the project progresses.
Telephone townhalls
We held two telephone townhalls in April and May 2020, providing the community an opportunity to learn more about the project, ask questions and provide feedback. We’ve included responses to the common questions asked in our Q&As section.
Regulatory process
We filed our application with our regulator, the British Columbia Utilities Commission (BCUC), on November 16, 2020. We are now awaiting a decision on this application, which we anticipate in 2023.
Other resources
We’ve been engaging with Indigenous communities, local governments and area residents as the project progresses. Materials related to these discussions are available below.
- Telephone town hall presentation - April/May 2020
- Information card - April 2020
- Project launch information bulletin - April 2020